
When a generator or other industrial machine stops working, the first explanation offered is often the wrong one. Mechanical and electrical failures can look the same at the outset, and a misdiagnosis leads straight to the wrong policy response and the wrong settlement.
This article walks through an anonymised claim we handled for the breakdown of an industrial diesel generator under the Mechanical/Electrical Breakdown extension of an Industrial All Risk (IAR) policy. It covers how we established the cause, how the repair costs were tested, and how underinsurance changed the outcome more than anything else.
A diesel generator has two halves: the engine, which is the prime mover, and the alternator, which turns the engine's mechanical energy into electricity. Each has its own typical faults.
Common mechanical failures include fuel delivery problems such as a failed pump or blocked injectors, loss of lubrication, overheating from cooling faults, and wear leading to component breakage.
Typical electrical failures are winding faults, short circuits, regulator failure, control panel faults and damage from external surges.
A generator that will not start, or stops without warning, could be suffering from fuel starvation or from a control fault. The symptoms overlap. In the case below, the first report pointed to an electrical surge. The real cause was mechanical.
The unit was an 800kVA soundproof diesel generator at the factory of a large steel manufacturer. It was one of three backup generators supporting the national grid supply, and it powered the factory, the administrative building and on-site expatriate housing during outages.
Maintenance was good. An in-house team carried out daily checks on water, oil and fuel levels, and preventive maintenance, including lubricant and filter changes, was done every 200 running hours. We reviewed the maintenance logs and found them satisfactory. Because the grid supply was generally reliable, the generators were not heavily used.
Valuation was another matter. A pre-loss survey had produced an inventory, but the declared value for this generator was only about a sixth of its actual replacement value at the time of loss. That gap decided the size of the settlement.
The generator was running normally after a grid outage when it shut down suddenly one afternoon in November 2024. The on-site team could not restart it and brought in an alternative 1000kVA generator to restore power.
The insured notified its broker and insurer promptly and called in the generator supplier's representative. Insurers then appointed us. Working with a consulting engineer, we visited the site, inspected the generator before any repair, interviewed key staff including the Electrical Maintenance Manager, and reviewed the documents.
The supplier's report attributed the breakdown to a "sudden electrical surge that resulted in mechanical failure" but did not commit to a root cause. We found no physical evidence of a surge: no burnt components and no signs of a short circuit.
Our technical analysis showed the diesel lift pump had failed. That starved the engine of fuel, causing it to stall, and caused consequential damage to the fuel system, specifically the six diesel injector nozzles.
The insured submitted a repair quotation from the supplier's representative, covering repairs and a visit charge. We went through it line by line.
The adjusted loss came out at roughly nine tenths of the quotation. The damaged parts had negligible salvage value.
With the cause confirmed as mechanical breakdown, the loss fell within the Mechanical/Electrical Breakdown extension of the IAR policy.
The policy carried an 85% condition of average. As the declared value was far below that threshold, average applied, and the adjusted loss was scaled by the ratio of declared value to replacement value. The insured was therefore entitled to only about a sixth of the adjusted loss.
The deductible for the breakdown extension, set by the sum insured tier, was then taken off. The net settlement we recommended was roughly an eighth of the original quotation. Underinsurance, not the cause of failure or the repair scope, was the largest single factor.